Scheduling unrelated parallel machines with resource-assignable sequence dependent setup times

Área de Investigación: Articulos Año: 2011
Tipo de publicación: Artículo
Autores: Ruiz, Rubén; Andrés, C
Revista: International Journal of Advanced Manufacturing Technology Volumen: 57
Número: 5-8 Páginas: 777-794
Nota:
Submitted to an international journal
Abstract:
A novel scheduling problem that results from the addition of resource-assignable setups is presented in this paper. We consider an unrelated par- allel machine problem with machine and job sequence- dependent setup times. The new characteristic is that the amount of setup time does not only depend on the machine and job sequence but also on the amount of resources assigned, which can vary between a minimum and a maximum. The aim is to give solution to real problems arising in several industries where frequent setup operations in production lines have to be carried out. These operations are indeed setups whose length can be reduced or extended according to the amount of resources assigned to them. The objective function considered is a linear combination of total completion time and the total amount of resources assigned. We present a mixed integer program (MIP) model and some fast dispatching heuristics. We carry out careful and comprehensive statistical analyses to study what characteristics of the problem affect the MIP model performance. We also study the effectiveness of the different heuristics proposed.
Versión digital
Retroceder